Project Experience Summaries: Government
Services:
Design/Engineering, Material Management,
Permitting, Project Management
Scope
of work:
DUC was contracted by a nationwide engineering
firm to design, engineer, permit, and construct a communications
system for the US Army Corps of Engineers. DUC engineered the project
from Maryland to inside the District of Columbia. DUC obtained permits
for both the Maryland portion of the work as well as the portion
in the District of Columbia. DUC provided project management for
the entire build as well as procuring all materials for the project.
The turnkey project was delivered
on-schedule to the Army.
Services:
Construction
Scope of work:
Through a long-term, continued relationship, the client awarded
DUC a communication and power conduit installation project on Langley
Air Force Base.
As the expanse of DUC's successful military projects
has grown, DUC has gained significant recognition for completing
sensitive projects in secured government environments. In this particular
scope-of-work, DUC trenched and placed a concrete encased duct bank
with multiple manholes. A challenging portion of the project specified
use of a 30" auger drill with steel casing along an active runway.
Additionally, the project required excessive depth for placement
of the duct bank. Throughout the deeper excavation, DUC had to maintain
continuous de-watering efforts when placing manholes and duct bank
due to the high water table.
Services:
Construction, Engineering, Permitting
Scope of work:
DUC engineered, permitted, and installed the OSP and ISP for a unspecified
government agency. DUC directional drilled the route to tie the
secured facility into an existing MFN conduit and then excavated
for two building entrances. The location of the building penetrations
required a tunneling operation under the building foundation for
the core drilling into building. DUC placed all EMT, inner-duct,
and pull boxes along route to inside the building to reach the client's
secured demarcation. The completion of the project consisted of
pulling the cable from the existing MFN hand-hole as well as new
hand-hole that was over-set on existing facilities into the customer's
equipment room inside of building. Restoration included asphalt,
concrete, and landscaping.
Services:
Construction, Design/Engineering, Project Management
Scope of work:
As the preferred contractor for Washington Metro Area Transit Authority's
(WMATA) passenger rail system, DUC was contracted by a world-leading
telecommunications provider for the installation of fiber optic
cable within WMATA's tunnel system. DUC designed, engineered, and
installed fiber optic cable for both the client and WMATA in the
tunnels. The work was performed only during a three-hour limited
work window from 1:30 AM to 4:30 AM. DUC maintains excellent communication
with the Transit Authority's telecommunications personnel, and as
a result, was able to utilize this limited daily window of production
to coordinate and deliver the project within budget and on-schedule.
Cable was installed with clips to the tunnel walls and pulled through
an existing manhole system as well as the passenger stations' plenary
areas. DUC has the most experience out of any other contractor performing
work within the WMATA system with over 70 miles completed for various
carriers to date. DUC is also certified with the CSX and Amtrak
systems for rail safety and cabling installation specifications
and tolerances.
Services:
Construction
Scope of work:
One of the pioneering companies in the "communications by light"
fiber optic throughput industry awarded DUC a communication lateral
into 2000 Pennsylvania Avenue, Washington, DC, just a few blocks
from the White House. The construction project entailed an open
cut approximately 320' along "I" Street for placement of (2) 4"
conduits. The sub-grade penetrations required DUC to X-ray and core
drill the building foundation. DUC then pulled fiber into building
for termination to our client's customer. DUC also provided and
placed a 4'X6'X4' manhole and tied into an existing manhole. DUC
served as the lead to coordinate project details with all parties
involved on the project. DUC was also contracted to conduct the
final milling and overlaying of "I" Street as well as the intersection
of 21st and "I" Street. All work was completed at night and the
project was delivered ahead of schedule.
Back to top
Home About Services Projects News Careers Contact